US
301 Waldorf Transportation Improvements Project
(Waldorf
Bypass)
In
2005 the State budgeted $5 million to resume the study for the proposed Waldorf
Bypass which the State Highway Administration (SHA) had abruptly stopped in
2002. The reason reported to the public
for halting the study was lack of funding.
The Citizens Against the Waldorf Bypass (CAWB) believes the study was
halted because of the prospective inability to get Federal Highway funding for
the project. The prospective funding
was endangered because of disagreement among Federal and Charles County
officials on the best alternative for transportation improvements in the
Waldorf area.
The
Environmental Protection Act and Clean Water Act require that in order for the
Federal Government to provide funds for a major transportation project, an
Environmental Impact Statement (EIS) must be approved by the Federal Highway
Administration (FHWA). The Draft
Environmental Impact Statement (DEIS) and its alternatives are rated by the
Environmental Protection Agency (EPA), and an unacceptable rating can kill the
project. Additionally, the US Army Corps
of Engineers (COE) must approve a Section 404 permit for any dredging or
filling in waters of the United States and jurisdictional wetlands in order for
the project to proceed. There are other
coordinating agencies, such as Fish and Wildlife and Marine Fisheries which
have an advisory role in this process.
Frequently
in the past, we have been told by our elected officials that this project has
been studied enough, and it is time to start building a bypass. In fact, until the studies required for the
preparation of the DEIS are completed nothing can be done.
Unfortunately
for our citizen taxpayers, this study was close to completion in 2001. The Preliminary Draft Environmental Impact
Statement had been prepared, but it was not circulated for final coordination
because of the negative comments of the cooperating agencies with respect to
both bypass options. EPA commented that
if a bypass was recommended they would consider giving the document an adverse
rating and recommend that COE deny a 404 permit. COE initially commented that an upgrade was
the only acceptable alternative; however, they later advised that, a western
bypass was the most environmentally damaging alternative, an eastern bypass may
be permitable, and they were willing to further study the eastern bypass. Subsequently, in a public meeting between SHA
and the Charles County Board of Commissioners, the President of the Board
advised SHA, we will not go east and we will not go through Waldorf. The Board’s unwillingness to accept the
anticipated results of the Federally required NEPA 404 process effectively
stopped any further progress on the DEIS, and no Federal funds could be made
available for transportation improvement in the Waldorf area.
The
Citizens Advisory Committee appointed by the Charles County Board of
Commissioners met monthly with SHA and County officials over a period of three
years reviewing all of the transportation planning and alternatives. They recommended US 301 be upgraded through
Waldorf based upon alternative 3, interchanges at major intersections with no
traffic lights on through lanes and separate local lanes, designed to minimize
right-of-way requirements. Despite this
recommendation by their advisory committee the Board of Commissioners approved
a Transportation Strategy using County funds to upgrade County roads, planning
for a portion of the proposed western Waldorf bypass from Berry Road near
Greensward Turf Farm to the US 301/Washington Ave/Turkey Hill Road
intersection, and to identify bypass right-of-way within Charles County from
Berry Road to US 301 at the north end of Waldorf. There were two reasons for this unusual
action: 1st The Prince
George’s County Council had passed a resolution forbidding a portion of a
western Waldorf bypass in Prince George’s County, and 2nd in a
public meeting, SHA had verbally advised the Charles County Board of
Commissioners that a western Waldorf bypass could not be built solely in
Charles County.
On
January 11, 2006, the Interagency Working Group (IAWG) for the preparation of
the DEIS held their first meeting for the current study. Since that time, several steps in the
preparation of the DEIS have been completed. The public workshops held March 20, 22, and
24, 2007 are one of the steps in the preparation of the DEIS.
By
February, 2007, SHA had presented only bypass options to the IAWG and the SHA
web site discussed three options: 1, 1A, and 2 for upgrading US 301 through
Waldorf. None of these options were
capable of satisfying the transportation requirements of the project, and would
thereby force the
selection of a
bypass. The CAWB prepared and circulated a memorandum
which requested that upgrade alternative 3 from the 2001 PDEIS, a full upgrade
through Waldorf with separated through and local lanes, be included in the
current study. This paper was provided
to the Federal cooperating agencies.
On Wednesday,
March 14, 2007 the week prior to the public workshops, the IAWG met and
considered the upgrades through Waldorf, including alternatives 3 and 4 from
the previous study. At the workshops,
upgrade alternative 3 was prominently identified as “NOT PREFERRED”, an obvious
attempt to get citizens not familiar with the previous efforts to support
either an upgrade that would not satisfy the transportation needs or a
bypass.
The NEPA/404
process is required by law and a great deal of taxpayers funds have been and
are being spent to prepare the DEIS. Despite
the attempts of the previous Charles County Board of Commissioners and SHA to
force an environmentally damaging bypass, the law requires that the alternative
which satisfies the transportation requirements and is least damaging to the
environment be selected unless there are over riding social and economic
impacts to the human environment.
The upgrade
alternative 3 presented in 2001 carried the local roads over US 301 at the
interchanges, thereby separating the local roads from the businesses in Waldorf
and maximizing the right-of-way requirements, increasing the impact on the
businesses. This caused many business
owners to oppose alternative 3.
Alternative 3 designed to minimize right-of-way requirements by carrying
US 301 over the local road and using urban, underground drainage can be built
with minimal additional right-of-way and is the alternative that meets the
transportation requirements with minimal impact to the environment.
SHA’s web site
has now been updated and is fairly accurate although some information is
presented in such a way as to enhance selection of a bypass. For more information we recommend visiting www.us301waldorf .org for background
information. Also, contact the CAWB at ewallace@olg.com
or 301-609-8262 if you have questions or desire additional information.
Contact SHA and
other members of the IAWG. Despite the
attempts of SHA and the County to force a bypass, the IAWG is a body of public
employees trying to do their jobs for us.
Let them know your recommendation and your appreciation of their
efforts.
Contact
information:
State Highway
Administration:........................................................................ SHawtof@sha.state.md.us
U. S. Army Corp
of Engineers:.......................................................................... Steve.Harman@nab02.usace.army.mil
Environmental Protection Agency: ................................................................. Magerr.Kevin@epamail.epa.gov
Federal Highway Administration:.................................................................... danw.johnson@fhwa.dot.gov
National Oceanic and Atmospheric Administration National Marine Fisheries: john.nichols@noaa.gov
Department of the
Interior Fish & Wildlife Service: ......................................... bill_schultz@fws.gov
Maryland Department of the Environment: ..................................................... eghigiarelli@mde.state.md.us
Department of Natural Resources: .................................................................. ggolden@dnr.state.md.us
-----Ernie Wallace